Case Studies
TRL Group
Huntsman Wilton (2021-2022)
Awarded a contract Working as the principal contractor for Huntsman on the reactor refurbishment project, this project saw TRL Group carry out an engineering survey
13th March 2023
No Comments
TRL Group
Acciona UK Ness Energy project EfW. (2021–2022)
Contract award to provide site management and manpower to erect circa 2000t of structural steelwork. Also design and detail and fabrication and supply of an
27th February 2023
No Comments
TRL Group
Strabag Ltd – Wilton Site (2018-2019)
Contract award to oversee and manage the dismantle of a segment factory in Austria, transport and erect the structure, fabricate and provide an additional 40t
27th September 2022
No Comments
Teesside Rigging and Lifting
Sirius Minerals Woodsmith Mine & Lockwood Beck
Contract award to provide consultancy, training, and development of a lifting procedures. Covering all rigging & lifting operations and acting as lifting technical authority for
27th September 2022
No Comments